Status as of Nov. 20, 2026. The Bipartisan American Affordability and Jobs Act (BAAJA) has passed the Senate only. The House's SPEED Act has passed the House only. Neither is law. Where this article describes what either bill "would" do, it refers to proposed text. Executive orders, agency rules and court decisions are labeled as final, proposed or blocked.
A Thursday-night vote, and a short runway
On the evening of Thursday, Nov. 19, the Senate passed BAAJA by 62 to 33. The 33 no votes came from 31 Democrats plus Republicans Josh Hawley of Missouri and Mike Rounds of South Dakota (Roll Call). Sens. Shelley Moore Capito (R., W.Va.), Mike Lee (R., Utah), Martin Heinrich (D., N.M.) and Sheldon Whitehouse (D., R.I.) wrote the bill. They introduced it as S. 5653 on Sept. 30. It runs to seven titles in two divisions: one for environmental review, water, wildlife and project certainty, and one for transmission, energy permitting and historic preservation (CRS R49506). Capito said it had threaded "a needle the likes of which this chamber has not seen" in a while (Roll Call).
Some details are still disputed. The Associated Press counted 15 Democrats voting yes (OPB/AP), and ENR reports a similar figure (ENR). Democracy Now's headline says 14 Democrats (Democracy Now). The two counts can be squared. Native News Online reports 14 Democrats plus Angus King of Maine, an independent who caucuses with Democrats (Native News Online), and Common Dreams' 15-name list includes King (Common Dreams). We have not seen the official roll call for final passage.
Inside Climate News reported that by Wednesday night, Nov. 18, eroding Democratic support had left supporters only six votes above the 60 needed, a margin consistent with that day's 65–31 cloture vote (Inside Climate News, Nov. 19).
The procedural record explains why the coalition looked fragile. The Senate's roll-call list shows cloture on a Capito substitute amendment (S.Amdt. 6883) to H.R. 2347, an unrelated tax bill used as a shell. Cloture passed 70–27 on Nov. 16, the amendment was adopted 69–27 on Nov. 18, and cloture on the bill passed 65–31 the same day (Senate roll-call list). Those tallies match news reports of the BAAJA votes, so the Senate-passed text is very likely that substitute.
The official record for the Nov. 16 vote shows 21 Democratic and independent yeas (Senate vote 264). By final passage the number had fallen to about 15. Heatmap tracked who peeled off. Hawley voted yes on the Nov. 9 procedural vote and no from Nov. 16 on, over the transmission provisions (Heatmap).
Something else fell away on the floor. Wyden and Merkley wanted votes on amendments barring data centers from federal land and from the bill's project-certainty protections. When those votes stalled, a negotiated manager's package was dropped (Roll Call). That package would have narrowed the historic-preservation exemptions, raised Historic Preservation Fund money by half, addressed eminent-domain concerns and refined the data-center exemptions.
The bill goes to the House after Thanksgiving (Roll Call). The House returns Nov. 30 (Native News Online). The lame duck ends when the 120th Congress convenes on Jan. 3, 2027 (Pillsbury). The vehicle carries a House number, so the House could in principle send it to the president by agreeing to the Senate amendment, without a conference. That is our reading of standard procedure. No source we found describes the House's plan. The White House issued a statement of administration policy supporting the bill (Roll Call).
The stakes for data centers and power are easy to see. Utilities' five-year forecasts of peak-load growth have climbed to 166 GW, from 24 GW three years earlier, and they expect about 90 GW of new data-center load by 2030, though Grid Strategies puts it closer to 65 GW (Utility Dive). Meanwhile, the U.S. completed just 322 miles of new transmission at 345 kV and above in 2024 (ACEG/Grid Strategies). BAAJA goes at both problems at once. It speeds up how the grid gets built, and it directly changes how data centers pay for it.
What the Senate bill would do
Environmental review and the courthouse door
Division A rewrites the National Environmental Policy Act, or NEPA. The bill states that NEPA produces an informational document and "does not mandate a particular outcome." It narrows what counts as a "major federal action." It lets agencies stack categorical exclusions (CEs) and borrow each other's. It lets state or other reviews that are "functionally equivalent" substitute for NEPA. And it lets agencies rely on programmatic reviews for 10 years instead of five (CRS R49506).
The bill adds new clocks. Agencies would have 60 days to certify an application as complete and 60 days to decide the level of review. Environmental assessments would remain due in one year and impact statements in two, deadlines first set in the 2023 Fiscal Responsibility Act. Other permits would be due within 90 to 120 days (IFP).
The biggest change is in the courts. Lawsuits would have to be filed within 150 days, in federal courts of appeals (CRS R49506). Today the general statute of limitations for such challenges can run to six years (Columbia CGEP). Standing would be limited to parties who commented during review and who face direct harm (sponsors' section-by-section). Where the only defect is under NEPA, courts could only send the decision back to the agency, which would get 180 days to fix it. Work could continue in the meantime (IFP). ENR notes that limited grounds for preliminary injunctions survive (ENR). A separate energy section gives lease sales, rights-of-way and other energy and mineral authorizations the same 150-day clock (CRS R49506).
Water, wildlife and historic sites
Under the Clean Water Act, state Section 401 certifications would be narrowed. For interstate transmission lines and gas pipelines, states would get nine months and could look only at "direct point-source discharges." States would also have to justify denials (IFP). Discharge permits would run 10 years instead of five. EPA's §404(c) veto would be time-limited. Wetland impacts under two acres would be deemed minimal (CRS R49506).
Endangered Species Act consultations would be cut from 90 to 60 days. States could take over consultation from the Fish and Wildlife Service. Challenges to biological opinions would go only to the D.C. Circuit (CRS R49506).
The bill would also narrow the actions subject to Section 106 of the National Historic Preservation Act. Tribes have fought that change hardest (CRS R49506; Roll Call).
Transmission: the part with no House counterpart
Division B is where BAAJA leaves the House bill behind. It would end the Energy Department's role in designating national-interest electric transmission corridors (NIETCs). Instead, it would let FERC issue construction permits for qualifying interstate lines if a state denies an application or fails to act within a year, with federal eminent domain behind the permit (sponsors' section-by-section; IFP).
Two voltage figures appear in coverage, and they describe different thresholds. Lines of 230 kV or more can qualify for FERC's backstop authority, and lines of at least 345 kV can be processed by FERC at the same time the state reviews them (ENR; IFP).
Several other changes reach across regions:
- A new Federal Power Act §225 would require neighboring regions to plan transmission jointly, under a FERC rule due within 180 days.
- FERC's approval of an interregional plan would not count as a major federal action under NEPA (sponsors' section-by-section).
- Federal rights of first refusal for incumbent utilities would be barred. State versions would survive.
- Generator interconnection and transmission planning would be merged over a 20-year horizon within 18 months (sponsors' section-by-section).
- FERC would have to require utilities to consider advanced transmission technologies.
- Reconductoring within existing rights-of-way would get its own categorical exclusion (CRS R49506).
Data centers pay their way, and permits stay put
Section 2107, titled "Ratepayer Protection," declares that charging data centers less than both embedded and incremental transmission costs is not just and reasonable. It would give FERC 270 days to revise its 1994 pricing policy, with lower costs available to customers that choose non-firm service. A proposed rule would follow within another 270 days, and a final rule within a year of that. The section also affirms states' power to set separate data-center rates (sponsors' section-by-section; CRS R49506). Holland & Knight describes state-level protections for data-center loads of 20 MW or more (Holland & Knight). Section 2114 would have the Energy Information Administration collect demand data from data centers, crypto miners included (CRS R49506).
Title IV is the "permit certainty" section. It would bar agencies from revoking or suspending federal authorizations in effect on or after Sept. 16, 2026, except for narrow causes such as court orders, fraud, permit violations or specified threats to public health and safety. The government would have to justify any such action by clear and convincing evidence, and damages would be paid from the federal Judgment Fund. The sponsors' summary caps damages at 50% of construction costs incurred, while IFP describes a range of 25% to 50% (sponsors' section-by-section; CRS R49506; IFP).
A companion section creates a "disparate treatment" cause of action. Developers could sue over patterns of improper denials or delays, with remedies the sponsors put at 50% to 100% of project costs; CRS describes recovery of up to full project costs (sponsors' section-by-section; CRS R49506). A substitute released before the Nov. 9 procedural vote stretched the comparison period from five years to ten. The shorter window would have been set almost entirely by the current administration's record (Inside Climate News, Nov. 10). Pillsbury reports that the substitute also carries nuclear enrichment, NRC staff-pay and DOE transparency provisions drawn from bills moving in the House (Pillsbury). We could not confirm their final form.
The bill does not directly change LNG export approvals, though its litigation and permit-certainty provisions would apply to LNG projects (Columbia CGEP). It also does not include the Mountain Valley Pipeline-style project approvals that were in earlier Senate bills (Roll Call).
The House bill and the House problem
The House passed the SPEED Act (H.R. 4776) on Dec. 18, 2025, by 221 to 196, with 11 Democrats in favor (ENR, Dec. 2025). It covers NEPA only. It limits reviewable effects to those with a "reasonably close causal relationship" to the project. It provides that federal funding alone does not make a project a major federal action. Its litigation terms match BAAJA's: a 150-day limit, standing restrictions and remand as the only remedy (CRS IF13180).
A late floor amendment exempted offshore wind from SPEED's permit-certainty protections. That left the administration free to cancel those projects (ENR, Dec. 2025). American Clean Power dropped its support over the change (Inside Climate News, Dec. 2025). BAAJA goes the other way, with a special rule protecting offshore projects whose stop-work orders courts later enjoined (IFP). The two chambers' positions on offshore wind are in direct conflict.
The House math is uncertain. Speaker Mike Johnson says the bill can pass. Reps. Scott Peters and Nikki Budzinski, both Democrats, have expressed support, and Roll Call reported the bill appears to have the votes to pass the House (Roll Call). Rep. Jared Huffman (D., Calif.), the likely next chair of the Natural Resources Committee, opposes lame-duck passage and wants hearings and amendments in the new Congress (Axios).
The midterms shape all of this. NPR and AP reported on Nov. 4 that Democrats won control of both chambers (OPB/NPR). Bracewell's Joe Brazauskas put the new Senate majority at "at least 54" seats (Bracewell). Final seat totals for both chambers were not confirmed in the reporting we reviewed.
After the election and before the Senate vote, analysts cut their odds of a lame-duck deal. Rapidan moved to 20% to 25%, and TD Cowen to 25% (Axios). Those estimates predate the vote, and no updated odds were available. Supporters of passing the bill now argue that any later bill would still need 60 Senate votes and the president's signature. Jenkins put it as "this federal permitting reform bill, or nothing until at least 2029" (AEI).
Much has already changed without Congress
Developers are already working under a looser regime, built through executive action, agency rules and one Supreme Court decision. Only one permitting change is enacted law. The One Big Beautiful Bill Act (P.L. 119-21, signed July 4, 2025) lets a project sponsor pay 125% of the expected cost of a NEPA review in exchange for a 180-day environmental assessment or a one-year impact statement (O'Melveny).
Executive and regulatory. Executive Order 14318 (final, July 23, 2025) defines "Qualifying Projects." A project qualifies by meeting any one of these tests: more than 100 MW of new load, at least $500 million of capital spending, a national-security role, or designation by a cabinet secretary. The order directs agencies toward categorical exclusions, FAST-41 coverage, a possible data-center nationwide wetlands permit and federal land offerings. It presumes that federal financial assistance covering less than half of a project's cost does not trigger NEPA (Federal Register). The order's list of covered power sources includes gas, coal, nuclear and geothermal, but not wind or solar.
The Council on Environmental Quality removed its NEPA regulations, first by interim rule in February 2025 and then by final notice on Jan. 8, 2026. Agencies now follow their own procedures, which generally expand exclusions and drop express cumulative-effects requirements (Venable; WilmerHale). In April 2026, QTS's Richmond campus became the first data center with FAST-41 coverage. The Army Corps is the lead agency, which shows how often a wetlands permit is the only federal hook (Permitting Council).
Judicial. In Seven County Infrastructure Coalition v. Eagle County (May 29, 2025), a unanimous Supreme Court called NEPA "a procedural cross-check, not a substantive roadblock" (WilmerHale). WilmerHale reviewed 449 lower-court rulings applying the decision in its first year and found that agencies won more than 80% of them. Agencies still lose mainly on cumulative effects and on plain procedural omissions.
Breakthrough Institute warns of a cost to this approach. With no binding regulations, agency standards are inconsistent, and the result invites litigation that only a statute can settle (Breakthrough). That argument is the strongest one for BAAJA that does not depend on its specific terms.
Technology selectivity. Interior added layers of review for wind and solar in 2025 and halted offshore projects. The courts have pushed back:
- A federal judge in Massachusetts enjoined several of the wind and solar restrictions on Apr. 21, 2026, for the plaintiffs only.
- Courts in five separate 2026 cases let offshore projects resume.
- The administration's "Wind Order" was vacated in New York v. Trump, and that ruling is on appeal at the First Circuit (Crowell & Moring).
That record is why Democrats insisted on Title IV. Whitehouse said the bill's success depends on the administration "getting wind turbines up and spinning" (Inside Climate News, Nov. 10).
FERC holds the large-load pen, for now
The most consequential federal decisions for data centers are being made at FERC, under existing law. On Oct. 23, 2025, the Energy Department used a rarely invoked authority to send FERC an advance notice of proposed rulemaking on large-load interconnection, built around a 20 MW threshold (FERC RM26-4). FERC did not issue a national rule. On June 18, 2026, it sent show-cause orders to six regional grid operators, preliminarily finding their tariffs unjust and unreasonable for lacking large-load and co-location rules. The orders define a large load as 50 MW or more connected above 69 kV. They cover study processes, cost-shift prevention, co-location, behind-the-meter generation and new services for flexible loads (Akin). After a 90-day abeyance, five operators' responses were due Nov. 16 and the Southwest Power Pool's on Nov. 20, according to a secondary outlet whose dates should be checked against FERC's docket (W4NEWS).
FERC has also shown where it thinks its authority ends. It ordered PJM to create new transmission services for co-located load in December 2025 (Utility Dive). Then, on Oct. 9, 2026, it rejected the core of PJM's large-load plan. That plan would have required "bring your own new capacity" and offered an interim curtailable service, and FERC found both intruded on state retail jurisdiction (Utility Dive). Twelve days later, the president posted that large data centers are "mandated by me to make their own electricity." Bisnow reported it was unclear whether any executive action would follow (Bisnow). The closest thing on paper is a voluntary Ratepayer Protection Pledge from March 4, signed by Amazon, Google, Meta, Microsoft, OpenAI, Oracle and xAI (White House).
That leaves a gap between FERC's limits and the White House's rhetoric, and Section 2107 is Congress's attempt to fill it. The states are not waiting:
- Texas's SB 6 sets disclosure rules, fees of $50,000 per MW and emergency curtailment for loads above 75 MW (Foley).
- Oregon created a separate rate class for loads of 20 MW or more (Legal 500).
- Before the midterms, New York Gov. Kathy Hochul froze permits for new hyperscale data centers for up to a year, and Texas Gov. Greg Abbott has halted new grid connections pending an audit (Fortune).
How each asset class would be affected
Transmission: the largest potential gain, and slow to arrive
For transmission, NEPA reform alone does little. The Niskanen Center ran the House bill against the history of TransWest Express, a line that took about 16 years to approve. It found only marginal gains, partly because the decisive lawsuit was not a NEPA case. The 150-day limit would, however, have barred the Cardinal Hickory Creek suit, which was filed 10 months after that line's review closed (Niskanen Center).
Columbia's Center on Global Energy Policy modeled reforms similar to BAAJA's planning and siting provisions. It found they could add about 100 GW of wind, solar and storage and 38 GW of interregional transmission by 2035, saving about $7 billion in 2035 across the modeled regions. CGEP describes these as analogues, not estimates of the bill itself (Columbia CGEP). The benefits would arrive slowly. They depend on FERC rulemakings, the regional plans that follow them, and the litigation that will follow both. Eminent domain is the political weak point: Hawley's defection and House Republican unease both turned on it.
Gas generation: permits are not the binding constraint
Gas now leads the interconnection queues. Gas capacity seeking interconnection rose 86% in a year to 253 GW, while solar, storage and wind each fell 16% to 19% (APPA/LBNL). Turbines, not permits, set the pace. GE Vernova's gas backlog and slot reservations reached 122 GW in the third quarter, against about 5 GW of quarterly shipments (Turbomachinery Magazine). Mitsubishi Power is signing contracts for delivery in 2031 to 2034 (S&P Global). Wood Mackenzie projects turbine prices near $600/kW by the end of 2027, up 195% since 2019, and expects about 63 GW of U.S. gas additions in 2026 to 2030 (Utility Dive).
The 253 GW in the queue is roughly four times what turbine supply supports this decade, by our arithmetic. Reform would matter later, once the turbines arrive.
Pipelines: the Clean Water Act change matters most
Recent pipeline fights in the Northeast turned on state Section 401 denials, not on NEPA. BAAJA's nine-month, point-source-only limit is aimed squarely at that veto. Outright denials are rare, at 0.8% of 7,503 state decisions from late 2023 to 2025, but they are decisive when they happen. Regional price gaps show the cost: Algonquin Citygate hit $16.37/MMBtu in January 2025, against $4.13 at Henry Hub (Columbia CGEP). Williams's Northeast Supply Enhancement line won its New York approvals and began construction in spring 2026, according to trade-press reports (Rigzone). LNG is not short of permits. Authorized exports stand at 49.8 Bcf/d, against about 20 Bcf/d operating (Columbia CGEP).
Nuclear: the bottleneck has moved past licensing
Executive orders, not BAAJA, have done most of the work here. The NRC finalized its Part 53 framework for advanced reactors in March 2026 (POWER Magazine). It issued TerraPower's Natrium construction permit and renewed the Robinson plant's license in under 12 months (ANS Nuclear News). DOE adopted a categorical exclusion for advanced reactors on its own sites (Federal Register).
Restarts show where the constraint now sits. Palisades paused fuel loading after a fuel assembly tilted, and its power-purchase agreements require service by March 2027. Crane is targeting 2027 and Duane Arnold early 2029. Together the three plants restore about 2.25 GW (Michigan Public). The binding constraints are now engineering, fuel and capital.
Geothermal: the clearest direct winner
Geothermal developers drill several exploration campaigns on federal land, so NEPA exclusions compress their timelines directly. BAAJA would move to annual lease sales, set drilling-permit deadlines, waive federal permits where the government owns less than half the subsurface, and let Interior recover processing costs from applicants (CRS R49506). It builds on BLM's existing approval of Fervo's Cape Station for up to 2 GW (Power Engineering).
Solar, wind and storage: certainty more than speed
About two-thirds of solar projects that went through a full impact statement faced litigation before development, according to a Stanford study. Yet 80% of clean-energy developers say they site projects specifically to avoid federal review (Columbia CGEP). Resources for the Future found that the time from final approval to operation was nearly identical for challenged and unchallenged projects (RFF).
For this sector the bill's value lies in Title IV's protection against political revocation, the new deadlines for rights-of-way on public land, and interconnection reform. Sponsor-cited models are more optimistic. SEIA projects that wind and solar would reach 37.4% of generation by 2035 under the bill, versus 19.6% without it. Rhodium projects 3% to 5% lower power prices (Heinrich release). Both are modeled advocacy figures, not observed outcomes.
What it means for data centers
The federal hook is usually power, not the building
A typical data center on private land and served by a utility touches few federal permits. Often the only one is a Corps wetlands permit. Law firms stress that NEPA still applies wherever there is federal action or funding (Legal 500). BAAJA's authors say the bill does not change the law on where data centers can be sited (Inside Climate News, Nov. 19). For most campuses, then, the bill's effect is indirect. It runs through the pipelines, lines and plants that feed them. The direct effects show up in three places: federal sites, on-site power and cost allocation.
Federal sites are a "bring your own power" product
Every federal site awarded so far pairs computing load with dedicated generation:
- Savannah River: NNSA selected Amentum to negotiate a phased lease for a 1 GW campus with about 2 GW of on-site generation, moving from gas to nuclear. It is not yet a final award (DOE/NNSA).
- Paducah: a $100 billion private campus with up to 4.6 GW of gas and batteries, targeting 2031 (Ashurst Perkins Coie).
- Portsmouth, Ohio: a planned 10 GW campus with $4.2 billion of transmission, opposed by residents over contamination and emissions (Ashurst Perkins Coie).
- Boulder City, Nev.: BLM approved the first data center on public land in June. That approval is now on administrative appeal (Ashurst Perkins Coie).
The Center for Western Priorities counts at least 35 BLM data-center applications covering more than 24,000 acres (Center for Western Priorities). Wyden called the bill a giveaway of public lands to tech companies, and his ban amendment never got a vote (Inside Climate News, Nov. 19). Expect the House to revisit the issue.
On-site power runs on EPA rules, not this bill
For behind-the-meter gas, EPA's 2026 rules matter more than BAAJA. A January turbine rule created a "temporary" class for units under 850 MMBtu/h that run up to 24 months at one site, exempt from full New Source Review. A May proposal would let foundations and building shells go up before air permits are issued (Greenberg Traurig). Both are contested. A Clean Air Act citizen suit argues that 50 turbines at an xAI site in Mississippi are not temporary, and how the January rule applies to operations like xAI's remains disputed (Greenberg Traurig).
Earthjustice's Meg Slattery says BAAJA does not address on-site generation at all (Inside Climate News, Nov. 19). On-site power is also costly. CGEP puts on-site gas at $101 to $107/MWh, against an $86 average industrial price, and expects about 40 GW of behind-the-meter gas by 2028 (Columbia CGEP).
Cost allocation becomes federal law, if enacted
Section 2107 would turn the ratepayer pledge into statute and send it through FERC rulemaking. Heinrich, citing Grid Strategies, says data centers would contribute about $55 billion to transmission over a decade, $35 billion more than under current policy (Heinrich release). That is a sponsor-cited estimate.
The political pressure behind the provision is observable. PJM's 2028/29 capacity auction cleared at its $325/MW-day cap, for a total cost of $16.4 billion, and PJM attributed much of the higher demand forecast to data centers (Utility Dive). Cornell researchers estimate operators currently pay about 38% of the infrastructure costs their growth causes (Fortune). Whitehouse's summary: "The day of data center freeloading ends when this bill passes" (Inside Climate News, Nov. 19).
The Data Center Coalition was still reviewing the text as of Nov. 19 (same source). For developers, the practical effect is that grid costs move from a cost shared across all ratepayers to a line item in the project budget. The discount for non-firm service makes flexibility something a developer can price.
Areas to watch for opportunity
This section describes where reform points, not what to buy. Powered land with existing interconnection rights becomes scarcer and more valuable when large loads must pay for new upgrades. That includes retired industrial sites, legacy DOE parcels and substations with spare capacity. This is our inference. No source we found quantifies it.
Flexible and curtailable load is becoming a tariff product. FERC's orders call for new transmission services for flexible loads (Akin), and Section 2107 prices non-firm service lower.
Grid-enhancing equipment and reconductoring would gain a categorical exclusion and a federal push toward adoption (CRS R49506; sponsors' section-by-section). GE Vernova's $9 billion purchase of Trench Group signals how scarce high-voltage components are (Turbomachinery Magazine).
Merchant and interregional transmission developers gain from the ban on federal rights of first refusal and from FERC backstop siting. Geothermal on federal land gains from annual lease sales. Small and aeroderivative gas accounted for 70% of recent turbine orders, which were for units under 100 MW (Utility Dive). Federal-site partnerships, with DOE as landlord and NEPA lead, are a 2028 to 2031 story.
Permitting services and software should also see demand. The bill's 150-day litigation window rewards fast, defensible records, and its "ePermit" interagency data system would standardize filings (CRS R49506).
Risks, and the case against
The largest risk is local opposition, and the bill does not touch it. Data Center Watch counted around 120 projects blocked or delayed in the first half of 2026, worth roughly $198 billion by our sum of its two quarterly figures. It also found that opposition groups more than doubled from the end of 2025, to 843 (Trending Topics). Pew found that 60% of Americans are uncomfortable with a new local data center (Pew). Voters sided against the industry in 40 of 41 local ballot measures (Fortune). Federal fast-tracking could deepen that resentment.
Critics' substantive objections center on courts and liability. Sierra Club objects that the bill hollows out the authority of the courts. Critics also say the Judgment Fund payouts invite suits. Jeremy Symons said "there's enormous incentive for companies to litigate," and argues that permit certainty could shield existing fossil plants from future rules (Latitude Media). Jen Duggan of the Environmental Integrity Project said the deal would "pave the way for even more fossil fuel projects" (OPB/AP).
Tribes and the National Congress of American Indians oppose the historic-preservation title (Native News Online). Democratic attorneys general asked for a delay to protect state water authority. California's office lists 16 signers, including D.C., while ENR reports 17 (California AG; ENR). EDF backed opening debate but said the bill "weakens vital protections for our air, water, and local communities" (EDF).
The empirical argument cuts both ways. Across all federal actions, NEPA litigation touches about 0.2% of decisions (Ruple & Race). The median impact statement already fell to 2.2 years in 2024 from 3.1 years in 2017 to 2020, before either bill existed (Columbia CGEP). Union of Concerned Scientists' David Watkins: "The Clean Water Act isn't the problem" (Common Dreams).
The other side has evidence too. Between a quarter and a third of final impact statements are challenged, and transmission siting averages about a decade (IFP). Energy appeals add about 3.9 years of delay on average (Breakthrough Institute). Both claims can hold at once. NEPA is rarely the constraint for the median federal action, but it is often the constraint for the large linear projects the grid needs.
Two practical risks remain. The first is durability. EPA's turbine and New Source Review rules, CEQ's guidance and agency procedures can be undone by a future administration in a way a statute cannot. The second is implementation. Almost every benefit in BAAJA runs through FERC, CEQ, Interior or EPA rulemakings that will themselves be litigated (Holland & Knight).
What to watch
- Nov. 20, 2026: SPP's response to FERC's large-load show-cause order is due. Answers to all six regional filings follow about 30 days after each response, in mid-to-late December (W4NEWS).
- About Nov. 23, 2026: the 18-month mark of the executive order directing an NRC rulemaking overhaul. The NRC chairman has conceded some final rules will be late (POWER Magazine).
- Nov. 30, 2026: the House returns. Watch whether leaders bring up the Senate amendment as is, change it (which would send it back to a Senate coalition that has already shrunk), or let it lapse. A government-funding deadline competes for floor time (Axios).
- Jan. 3, 2027: the 120th Congress convenes and the lame duck ends (Pillsbury).
- If BAAJA is enacted: FERC's interregional planning rule would be due within 180 days and its data-center pricing revision within 270 days. Consolidated interconnection planning would be due within 18 months (CRS R49506).
- Pending, no date: the First Circuit appeal in New York v. Trump (No. 26-1174), the administrative appeal of BLM's Nevada data-center approval, the final EPA "begin actual construction" rule, and the xAI air suit (Crowell & Moring; Ashurst Perkins Coie; Greenberg Traurig).
- March 2027: the Palisades power-purchase agreement deadline. Crane's restart is targeted for 2027 (Michigan Public).
The bottom line
The most durable part of this week's vote may be one that has little to do with permitting speed. NEPA reform is mostly locking in gains that courts and agencies have already delivered. The genuinely new parts of BAAJA are federal transmission planning and siting, and a statutory rule that data centers pay the grid costs they cause. Both are slow to arrive and dependent on later rulemaking, and both outlast any single administration. If the House lets the bill lapse, cost allocation will still move forward, through FERC dockets and state statutes, more slowly and less evenly. Transmission reform would wait for a Congress and a president who agree.
For developers, the limits on power through 2030 are turbines, transformers, queues and neighbors. Permitting reform mostly shapes the decade after that. Projects that will do best under either outcome are already paying their own grid costs and carry little risk if those costs rise.
Sources
- "Sweeping permitting overhaul passes Senate, on to House," Roll Call, Nov. 19, 2026. https://www.rollcall.com/2026/11/19/sweeping-permitting-overhaul-passes-senate-on-to-house
- "Senate Passes Permitting Reform Bill to Speed Infrastructure Construction," ENR, Nov. 20, 2026. https://www.enr.com/articles/64380-senate-passes-permitting-reform-bill-to-speed-infrastructure-construction
- "Senate passes bipartisan permitting reform bill," CBS News, Nov. 2026. https://cbsnews.com/news/senate-bipartisan-permitting-reform-bill-energy-baaja-trump
- "Senate Passes Permitting Reform Bill with Support of 14 Democrats, Including Leader Chuck Schumer," Democracy Now, Nov. 20, 2026. https://www.democracynow.org/2026/11/20/headlines/senate_passes_permitting_reform_bill_with_support_of_14_democrats_including_leader_chuck_schumer
- "Senate passes BAAJA," Common Dreams, Nov. 20, 2026. https://www.commondreams.org/news/senate-passes-baaja
- "Bipartisan permitting bill: data center impact," Inside Climate News, Nov. 19, 2026. https://insideclimatenews.org/news/19112026/bipartisan-permitting-bill-data-center-impact/
- "Senate advances permitting bill," Inside Climate News, Nov. 10, 2026. https://insideclimatenews.org/news/10112026/senate-advances-permitting-bill/
- Roll Call Votes, 119th Congress, 2nd Session, U.S. Senate, accessed Nov. 20, 2026. https://www.senate.gov/legislative/LIS/roll_call_lists/vote_menu_119_2.htm
- Roll Call Vote No. 264 (cloture on S.Amdt. 6883), U.S. Senate, Nov. 16, 2026. https://www.senate.gov/legislative/LIS/roll_call_votes/vote1192/vote_119_2_00264.htm
- Senate daily coverage of the vote shifts, Heatmap, Nov. 18, 2026. https://heatmap.news/daily/senate-vote-permitting-bil
- "House Nuclear Licensing and Fuel-Cycle Reforms in the Lame-Duck Session," Pillsbury Winthrop Shaw Pittman, Nov. 17, 2026. https://www.pillsburylaw.com/en/news-and-insights/us-house-nuclear-licensing-fuel-cycle-reforms-lame-duck-session.html
- "Despite strong tribal opposition, U.S. Senate approves BAAJA in late-night vote," Native News Online, Nov. 2026. https://nativenewsonline.net/sovereignty/despite-strong-tribal-opposition-u-s-senate-approves-baaja-in-late-night-vote/
- "Grid Strategies: some load forecasts using unrealistically high load factors," Utility Dive, Nov. 19, 2025. https://www.utilitydive.com/news/some-load-forecasts-using-unrealistically-high-load-factors-grid-strateg/805927/
- "Fewer New Miles," Americans for a Clean Energy Grid and Grid Strategies, July 2025. https://cleanenergygrid.org/wp-content/uploads/2025/07/ACEG_Grid-Strategies_Fewer-New-Miles-2025.pdf
- CRS Report R49506, Bipartisan American Affordability and Jobs Act of 2026 (S. 5653), Congressional Research Service, Nov. 5, 2026. https://www.everycrsreport.com/files/2026-11-05_R49506_ed46053de5d7f54d481a79f9cc90a922997b23c7.pdf
- "How the permitting deal works," Institute for Progress, Oct. 12, 2026. https://ifp.org/how-the-permitting-deal-works/
- "What the Bipartisan American Affordability and Jobs Act Means for the U.S. Energy System," Columbia University Center on Global Energy Policy, Oct. 27, 2026. https://www.energypolicy.columbia.edu/publications/what-the-bipartisan-american-affordability-and-jobs-act-means-for-the-u-s-energy-system/
- BAAJA section-by-section (sponsor summary; House Western Caucus copy), 2026. https://westerncaucus.house.gov/uploadedfiles/baaja_section-by-section.pdf
- "Bipartisan Senate committee leaders release permitting reform text," Holland & Knight, Oct. 1, 2026. https://www.hklaw.com/en/insights/publications/2026/10/bipartisan-senate-committee-leaders-release-permitting-reform-text
- "House passes NEPA review overhaul," ENR, Dec. 19, 2025. https://enr.com/articles/62251-house-passes-nepa-review-overhaul
- CRS In Focus IF13180, The SPEED Act (H.R. 4776), Congressional Research Service, Mar. 10, 2026. https://www.everycrsreport.com/reports/IF13180.html
- "SPEED Act passes in House, threatens clean power projects," Inside Climate News, Dec. 18, 2025. https://insideclimatenews.org/news/18122025/speed-act-passes-in-house-threatens-clean-power-projects/
- "2026 midterms: Democrats win the Senate," OPB/NPR, Nov. 4, 2026. https://www.opb.org/article/2026/11/04/2026-midterms-democrats-win-the-senate/
- "Democratic gains boost skepticism of permit bill's lame-duck prospects," Bracewell (via Inside EPA), Nov. 4, 2026. https://www.bracewell.com/news-events/democratic-gains-boost-skepticism-of-permit-bills-lame-duck-prospects/
- "Democrats' midterm wins cloud lame-duck permitting bill," Axios, Nov. 5, 2026. https://www.axios.com/2026/11/05/democrats-midterms-lame-duck-permitting-bill
- Roger Pielke Jr., "BAAJA now or BAAJA later?," American Enterprise Institute, Nov. 20, 2026. https://www.aei.org/commentary/baaja-now-or-baaja-later/
- "The One Big Beautiful Bill Act offers expedited NEPA review for a fee," O'Melveny & Myers, 2025. https://omm.com/insights/alerts-publications/the-one-big-beautiful-bill-act-offers-expedited-nepa-review-for-a-fee
- Executive Order 14318, "Accelerating Federal Permitting of Data Center Infrastructure," Federal Register 90 FR 35385, July 28, 2025. https://www.govinfo.gov/content/pkg/FR-2025-07-28/html/2025-14212.htm
- "CEQ formally rescinds its NEPA implementing regulations," Venable, Jan. 26, 2026. https://www.venable.com/insights/publications/2026/01/ceq-formally-rescinds-its-nepa-implementing
- "One year after Seven County: trends in NEPA review and litigation risk," WilmerHale, June 4, 2026. https://www.wilmerhale.com/en/insights/client-alerts/20260604-one-year-after-seven-county-trends-in-nepa-review-and-litigation-risk
- "First data center project gains Permitting Council's FAST-41 coverage," Federal Permitting Improvement Steering Council, Apr. 2, 2026. https://permitting.gov/newsroom/press-releases/first-data-center-project-gains-permitting-councils-fast-41-coverage
- "The widening vacuum of NEPA law," Breakthrough Institute, n.d. (post-2025). https://thebreakthrough.org/issues/energy/the-widening-vacuum-of-nepa-law
- "Federal court blocks Trump administration policies restricting wind and solar permitting," Crowell & Moring, 2026. https://www.crowell.com/en/insights/client-alerts/federal-court-blocks-trump-administration-policies-restricting-wind-and-solar-permitting
- Docket RM26-4-000, Large Load Interconnection, Federal Energy Regulatory Commission. https://www.ferc.gov/rm26-4
- "FERC issues landmark show-cause orders on large-load interconnection," Akin Gump, June 18, 2026. https://www.akingump.com/en/insights/blogs/speaking-energy/ferc-issues-landmark-show-cause-orders-on-large-load-interconnection
- "FERC: five grid operators' large-load show-cause filings due Nov. 16, 2026," W4NEWS, Nov. 14, 2026. https://w4news.org/ferc-five-grid-large-load-show-cause-filings-november-16-2026/
- "FERC orders PJM to create co-location transmission services," Utility Dive, Dec. 19, 2025. https://www.utilitydive.com/news/ferc-pjm-colocation-data-center/808368/
- "FERC rejects PJM large-load interim service and bring-your-own-capacity proposals," Utility Dive, Oct. 12, 2026. https://www.utilitydive.com/news/ferc-pjm-large-load-interconnection-iras-byonc/832716/
- "Trump: data centers 'mandated' to supply own electricity, should pay dividend to communities," Bisnow, Oct. 21, 2026. https://www.bisnow.com/news/national/data-center-community-relations/trump-data-centers-mandated-to-supply-own-electricity-should-pay-dividend-to-communities
- "Fact Sheet: President Donald J. Trump advances energy affordability with the Ratepayer Protection Pledge," The White House, Mar. 4, 2026. https://www.whitehouse.gov/fact-sheets/2026/03/fact-sheet-president-donald-j-trump-advances-energy-affordability-with-the-ratepayer-protection-pledge/
- "Public Utility Commission of Texas issues proposed rules for large-load interconnection," Foley & Lardner, Mar. 31, 2026. https://www.foley.com/insights/publications/2026/03/public-utility-commission-of-texas-issues-proposed-rules-for-large-load-interconn/
- "Environmental permitting for AI data centers: federal acceleration, federal lands and state resistance," Squire Patton Boggs via Legal 500, May 28, 2026. https://www.legal500.com/intelligence/united-states/environment/environmental-permitting-for-ai-data-centers-federal-acceleration-federal-lands-and-state-resistance
- "Democrats, the AI data center backlash and electricity costs," Fortune, Nov. 17, 2026. https://fortune.com/2026/11/17/democrats-ai-data-center-backlash-electricity-costs-regulation-economic-growth/
- "Can the SPEED Act break transmission gridlock? We put it to the test," Niskanen Center, Oct. 21, 2025. https://www.niskanencenter.org/can-the-speed-act-break-transmission-gridlock-we-put-it-to-the-test
- "Backlog of power plants seeking transmission grid connection eased somewhat in 2025: LBNL," American Public Power Association, 2026. https://www.publicpower.org/periodical/article/backlog-power-plants-seeking-transmission-grid-connection-eased-somewhat-2025-lbnl
- "GE Vernova Q3 2026: gas power backlog reaches 122 GW; Trench acquisition," Turbomachinery Magazine, Oct. 29, 2026. https://www.turbomachinerymag.com/view/ge-vernova-q3-2026-gas-power-backlog-122-gw-trench-acquisition
- "Interview: Mitsubishi Power gas turbine orders stretch to 2030 amid AI, security demand," S&P Global Commodity Insights, July 3, 2026. https://www.spglobal.com/energy/en/news-research/latest-news/energy-transition/070326-interview-mitsubishi-power-gas-turbine-orders-stretch-to-2030-amid-ai-security-demand
- "Gas turbine supply crunch set to raise prices 195% by 2027: WoodMac," Utility Dive, Apr. 9, 2026. https://www.utilitydive.com/news/gas-turbine-supply-crunch-set-to-raise-prices-195-by-2027-woodmac/816904/
- "Construction begins for Transco gas pipeline expansion," Rigzone, Apr. 15, 2026. https://www.rigzone.com/news/construction_begins_for_transco_gas_pipeline_expansion-15-apr-2026-183455-article/
- "How Trump's EO 14300 is reshaping NRC nuclear licensing and regulation," POWER Magazine, May 20, 2026. https://www.powermag.com/how-trumps-eo-14300-is-reshaping-nrc-nuclear-licensing-and-regulation/
- "Nuclear EOs, one year later," ANS Nuclear News, May 22, 2026. https://www.ans.org/news/2026-05-22/article-8066/nuclear-eos-one-year-later/
- "Categorical Exclusion for Advanced Nuclear Reactors," U.S. Department of Energy, Federal Register, Feb. 2, 2026. https://www.federalregister.gov/documents/2026/02/02/2026-02071/categorical-exclusion-for-advanced-nuclear-reactors
- "United States nuclear plants: Palisades, Michigan," Michigan Public, Oct. 16, 2026. https://www.michiganpublic.org/transportation-infrastructure/2026-10-16/united-states-nuclear-plants-palisades-michigan
- "Geothermal gains: Fervo's next-gen project approved as BLM aims to speed up resource discovery," Power Engineering, Oct. 22, 2024. https://www.power-eng.com/renewables/geothermal-gains-fervos-next-gen-project-approved-as-blm-aims-to-speed-up-resource-discovery/
- "Taking green energy projects to court: NEPA review and court challenges to renewable energy," Resources for the Future, Aug. 4, 2025 (updated Oct. 2, 2025). https://www.rff.org/publications/reports/taking-green-energy-projects-to-court-nepa-review-and-court-challenges-to-renewable-energy/
- "Heinrich: Senate passage of landmark bipartisan permitting deal will lower electricity bills, hold data centers accountable," Office of Sen. Martin Heinrich, Nov. 19, 2026. https://www.heinrich.senate.gov/newsroom/press-releases/heinrich-senate-passage-of-landmark-bipartisan-permitting-deal-will-lower-electricity-bills-hold-data-centers-accountable-create-over-one-hundred-thousand-jobs-reduce-carbon-emissions
- "DOE/NNSA selects Amentum to negotiate lease for AI data center at Savannah River Site," U.S. Department of Energy, July 20, 2026. https://www.energy.gov/node/4859533
- "Federal lands as the new AI data center frontier," Ashurst Perkins Coie, Aug. 7, 2026. https://www.ashurstperkinscoie.com/en/insights/federal-lands-as-the-new-ai-data-center-frontier/
- "BAAJA backers admit permitting bill will speed data center construction, including on public lands," Center for Western Priorities, Nov. 2026. https://westernpriorities.org/2026/11/baaja-backers-admit-permitting-bill-will-speed-data-center-construction-including-on-public-lands/
- "Data centers and air quality: recent changes and important considerations for developers," Greenberg Traurig, June 23, 2026. https://www.gtlaw.com/en/insights/2026/6/data-centers-and-air-quality-recent-changes-and-important-considerations-for-developers
- "PJM capacity auction hits price cap, falls short of reserve target," Utility Dive, July 15, 2026. https://www.utilitydive.com/news/pjm-capacity-auction-price-cap-reserve-shortfall/825282/
- "U.S. data center opposition, Q2 2026," Trending Topics (summarizing Data Center Watch), Sept. 24, 2026. https://www.trendingtopics.eu/us-data-center-opposition-q2-2026/
- "Americans' views of data centers have turned more negative," Pew Research Center, Sept. 22, 2026. https://pewresearch.org/short-reads/2026/09/22/americans-views-of-data-centers-have-turned-more-negative/
- "Why green groups won't endorse the Senate permitting deal," Latitude Media, Oct. 23, 2026. https://www.latitudemedia.com/news/why-green-groups-wont-endorse-the-senate-permitting-deal/
- "Senate approves bill to speed up permitting reviews, force data centers to pay for energy costs," OPB/Associated Press, Nov. 20, 2026. https://www.opb.org/article/2026/11/20/senate-approves-bill-to-speed-up-permitting-reviews-force-data-centers-to-pay-for-energy-costs/
- Attorney General Bonta and multistate coalition urge Senate to postpone BAAJA vote, California Office of the Attorney General, Nov. 9, 2026. https://oag.ca.gov/node/632618
- "Statement: U.S. Senate should adopt permitting bill amendments to protect public health," Environmental Defense Fund, Nov. 16, 2026. https://www.edf.org/media/statement-us-senate-should-adopt-permitting-bill-amendments-protect-public-health-and
- John C. Ruple and Kayla M. Race, "Measuring the NEPA Litigation Burden," University of Utah S.J. Quinney College of Law, 2019. https://dc.law.utah.edu/cgi/viewcontent.cgi?article=1008&context=stegner_pubs
- "No, NEPA really is a problem for clean energy," Institute for Progress, Aug. 17, 2023. https://ifp.org/no-nepa-really-is-a-problem-for-clean-energy/
- "Understanding NEPA Litigation," Breakthrough Institute, n.d. https://thebreakthrough.org/issues/energy/understanding-nepa-litigation
- "Congress senioritis: lame duck and shutdown, 2026," Axios, Nov. 9, 2026. https://www.axios.com/2026/11/09/congress-senioritis-lame-duck-shutdown-2026